Services
 

 
Supporting Information
 


 
 
Home >  Emergency Site Investigation
Emergency Site Investigation

 


Immediate mobilisation


Lankelma carried out an emergency rail site investigation in North London.  We were able to mobilise onto site immediately the client needed us.


6m reach

UK14, the 360 road-rail CPT rig was used.  Its 6m reach enabled tests to be carried out from one track.  This proved to be extremely useful as there were a number of other activities being carried out at the same time.


8 CPTs, 1piezometer

Over one shift, 8 CPTs were carried out to a maximum test depth of 14m.  A 
standpipe piezometer was also installed to a depth of 6m.  The CPT results were processed directly the job was finished and sent through within hours.
 

Emergency Site Investigation



contact Lankelma
tel: +44 (0)1797 280050

or use our contact form