Lankelma carried out an emergency rail site investigation in North London. We were able to mobilise onto site immediately the client needed us.
6m reach
UK14, the 360 road-rail CPT rig was used. Its 6m reach enabled tests to be carried out from one track. This proved to be extremely useful as there were a number of other activities being carried out at the same time.
8 CPTs, 1piezometer